Aug 31, 2018 | ,

121 Bank Street, East Victoria Park – Project Update August 2018

Since our last update, the slabs have cured and the bricklayers have commenced constructing the internal and external walls. The bricklayers have a large team and therefore are scheduled to reach plate height across all of the villas by late September (weather permitting). At that point in time the roof carpenters will commence framing up the roofs.

Construction is on schedule with practical completion anticipated for March next year.

I look forward to updating you next month, but should you have any queries in the meantime, or would like to talk to one of our sales agents about securing one of the villas, please contact me on (08) 6144 0700 or 0451 533 440.

Regards,
Travis McKenzie