Almond Lane, Ardross – Project Update May 2016
Good progress was made on site during the month of May. Brickwork is now complete on the rear building and all window and door frames have been installed to the apartments.
The 1st floor slab was poured to the front townhouses and work will commence shortly on the brickwork of the top floor.
Work will also commence shortly on the roof framing to the apartment building.
We look forward to updating you on progress next month. At this stage there is no change to our expected completion date which remains at December this year. If you have any questions, please don’t hesitate to call.
Matt Evans