4 Downey Drive, Manning – Project Update April 2018
Work onsite slowed for the majority of April while the builder waited for the first floor slabs to finish curing. As soon they were able to, the bricklayers mobilised back to site and commenced constructing the first floor walls. The bricklayers have commenced at lot 5 and are working their way forward to lot 1.
The focus for May will be to finish the construction of the first floor walls and then the roof carpenters will commence framing up the roofs.
Construction is still on schedule with practical completion anticipated for December this year.