4 Downey Drive, Manning – Project Update February 2018

During February the ground floor brickwork for units 3, 4 & 5 was completed up to the first floor slab level.  This then allowed the formwork for their first floor slabs to be constructed.  Once completed, the electricians laid their conduits and canisters and the plumbers set out their penetrations and collars.  The reo was then installed in preparation for the concrete pour in the coming days.

After the bricklayers had completed the ground floors of units 3, 4 & 5 they then moved onto units 1 and 2 where they are very close to reaching the first floor slab level.

Construction is currently on schedule with practical completion anticipated for December this year.