Mar 30, 2018 | ,

4 Downey Drive, Manning – Project Update March 2018

During March the first floor slabs for units 3, 4 & 5 were poured and they are now being left to cure for 21 days.  The bricklayers completed unit 1’s walls, which also allowed unit 2’s slab to be poured, and that is now also curing.

Internally the electrical and plumbing contractors chased in all of their ground floor services.  Once completed this allowed the plasters to complete their grey float coats.

Construction is still on schedule with practical completion anticipated for December this year.

I look forward to updating you next month, but should you have any queries in the meantime, or would like to talk to one of our sales agents about securing one of the apartments or townhouses, please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

 