Sep 21, 2017 | ,

4 Downey Drive, Manning – Project Update September 2017

Over the preceding month, Celsius Developments has worked closely with its architect, engineers and consultants to finalise the working drawings for the development.  We are aiming to have the working drawings completed and ready to issue for tender by the end of September.

The tender process should take approximately 3 weeks, and at its conclusion, a builder will be selected.  We are still aiming for construction to commence in November.

In addition, we are continuing to work with Celsius Property to develop the marketing plan with the target of a mid October marketing launch.  If you are interested in talking to one of our sales agents about being one of the first to secure one of the apartments or townhouse I encourage you to call the office on (08) 6144 0700.

I look forward to updating you next month, but should you have any queries in the meantime please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

Regards,

Travis McKenzie