Lucent Claremont – September Update 2020

Good progress is being made on site as we continue to push for practical completion in early December.

All bifold screens and façade trees have been installed on the eastern elevation and installation of screens will commence on the western elevation this week. The elevators in the building have been commissioned and works are well advanced on the residents lounge with ceiling and wall linings now in place. The residential entry lobby is also progressing with wall framing installed in preparation for the feature timber cladding to be installed in the next two weeks.

Internally, the cabinets are progressing well on level four with stone benchtops currently being fitted off. Electrical and plumbing fit-offs are also continuing on level four while ceilings and walls are now in place in the penthouse apartments. Tiling is complete on level four and will commence on the penthouse level this week. The feature timber soffits have been installed on the penthouse balconies and the external faces of the balconies have now been rendered.

We are pleased to report that sales at Lucent have continued to be strong with only four apartments now remaining for sale. If you would like any information on the remaining apartments please contact our sales team and they will be happy to arrange an appointment.

We look forward to updating you on our progress in October, but if you have any questions in the meantime please don’t hesitate to call.

Regards,
Matt Evans