Park Terraces – September Update 2021
An improvement on the weather has allowed for some significant progress for the month of September. The following occurred onsite during the month:
Ground Floor – All Terraces had their mechanical, hydraulic and electrical services installed. The plasterboard was hung and all internal doorframes installed. Terraces 1 to 6 had their window pressings installed, with the windows for those terraces to be installed next week.
First Floor – All Terraces have had the render applied to the party walls. The service trades commenced installing the mechanical, hydraulics and electrical services.
Second Floor – The timber walls and roof framing are nearly completed for Terraces 1 to 6.
Looking forward to next month:
Ground Floor – All Terraces will have the white set internal render applied to their walls. The floors will be polished for those Terraces who requested polished concrete floors. The windows will be installed.
First Floor – Weather permitting, the white set to the party walls will be applied and the windows will be installed to the west elevation of Lots 11 and 12. Service trades will continue installing their services.
Second Floor – Roof framing and sheeting to continue across all Terraces.
The builder is still aiming for a practical completion date of late February/early March.
I look forward to updating you next month, but in the meantime should you have any queries please feel free to contact me on (08) 6144 0700 or 0451 533 440.
Regards,
Travis McKenzie