Roberts Street, West Osborne Park – April Update 2020
The focus during April has been to continue the pipework for the fuel systems, to complete the electrical and plumbing prelays and to commence construction of the shop. As you will see from the pictures the shop’s slab has been poured and perimeter walls erected.
Due to issues associated with COVID-19 there have been some delays with the fuel system installation which has had a knock-on effect to the commencement date for the canopy. Construction of the canopy is now due to commence in May.
The focus during May will be to complete and test the fuel systems, make substantial progress on the shop and pour the driveways.
I look forward to updating you next month, however, should you have any queries in the meantime please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.
Regards,
Travis McKenzie