Jun 30, 2020 | ,

Roberts Street West, Osborne Park – June Update 2020

With practical completion only a matter of weeks away the site is really taking shape.

Since our last update, externally the builder has poured the forecourt, driveways and kerbs and sheeted the majority of the canopy. The shop windows were also installed which allowed good progress to be made internally. All of the plasterboard was hung and painted, the air conditioning and refrigeration installed and the fridge doors hung. The vinyl flooring is currently being laid.

The builder is aiming to reach practical completion by early to mid July at which point Coles Express will commence their fitout.

I look forward to updating you next month, however, should you have any queries in the meantime please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

Regards,
Travis McKenzie