The Fitz, North Perth – Project Update March 2016

The apartments in the front building (ie apartments 1 to 14 and 23 to 29) now have their kitchen cabinets and bathroom vanities installed and all of their tiling completed to the kitchen, bathroom and balcony.  The majority have also had their toilets installed.  Floorboards have been laid (and protected) in those apartments who choose the upgrade.  The painters have also completed their undercoats in the majority of those apartments.

 

The apartments in the rear building (ie apartments 15 to 22 and 30 to 37) are not as progressed as the front building, however, all have now had their white set applied and the tiling of the bathrooms is completed.  The kitchens have been delivered and installation has commenced in a number of the apartments.

 

Externally the courtyards to the apartments along Fitzgerald Street have been constructed and ground works have commenced for the water meters and fire hydrants.

 

Despite the builder advising us last month that they had made up time and were hoping to finish a month early this is no longer looking like a possibility and they are once again advising us that practical completion should occur as originally planned around the middle of August with settlements to occur 6 to 8 weeks after that.

 

If you have any queries in the meantime please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440.

 