Whatley Apartments – Development Update April 2016

Internally the apartments are completed except for carpet and a final clean. As soon as the cleaners have completed cleaning the apartments (which should be by the end of this week), the carpet layers will be able to lay the carpet. Once this is completed the builder’s attention will then turn to completing the internal corridors and lobbies. 

Externally the last remaining items to be completed are the installation of the remaining balustrades, bitumen and paving to be laid in the carpark and entry, landscaping to be planted and the front fence to painted and the infill panels installed.

The builder has advised that they are still on schedule to complete construction by the middle of May with settlements to occur 6 to 8 weeks later.

All buyers should have received a letter by now from Celsius Property outlining what steps will occur leading up to settlement. If you have not received this letter please contact the Celsius office on (08) 6144 0700

I look forward to providing you our final update next month, in the meantime please do not hesitate to contact me on (08) 6144 0700 or 0451 533 440 if you have any questions.

Regards,
Travis